GROUP: |
Building |
TYPE: |
Bldg-Alter/Repair |
SUB-TYPE: |
Commercial |
PRIMARY USE: |
(13) Office |
WORK DESCRIPTION: |
MODIFICATION TO ROOFTOP WTF INSTALLATION OF 3 NEW ANTENNAS, INSTALL 3 NEW ANTENNA MOUNTS, REMOVE AND REPLACE 3 ANTENNAS, "BE RIGHT" |
PERMIT ISSUED: |
Yes |
PERMIT ISSUE DATE: |
07/27/2016 |
ISSUING OFFICE: |
Metro |
CURRENT STATUS: |
Permit Finaled |
CURRENT STATUS DATE: |
09/26/2016 |
|
|
Submitted |
05/19/2016 |
APPLICANT |
Assigned to Plan Check Engineer |
05/20/2016 |
JAMES DETCHMENDY |
Corrections Issued |
05/24/2016 |
JAMES DETCHMENDY |
Quality Review Completed |
05/26/2016 |
DAVID CHANG |
Plan Check Approved |
07/27/2016 |
JAMES DETCHMENDY |
Issued |
07/27/2016 |
LADBS |
Permit Finaled |
09/23/2016 |
KATY RAMIREZ |
"D" conditions |
Cleared |
07/12/2016 |
TINA VACHARKULKSEMSU |
Plan Approval |
Cleared |
07/12/2016 |
TINA VACHARKULKSEMSU |
ZA Case |
Cleared |
07/12/2016 |
TINA VACHARKULKSEMSU |
|